PROJECT GALLERY
01 / PROJECT OVERVIEW
THE PROJECT
KGK Scaffolding was entrusted with delivering a substantial scaffolding and access package across all six residential blocks at Radial Apartments, Point Pleasant, London. A major six-block residential scaffolding and access scheme involving extensive scaffold access, specialist scaffold security systems and ongoing coordination across an occupied London development.
Situated within the Point Pleasant riverside quarter in Wandsworth, Radial Apartments forms part of an area that has transformed from its industrial past into a modern residential neighbourhood. The six-block development occupies a prominent location close to the River Thames and presented KGK with a significant multi-phase access requirement across the wider site.
The project was delivered as part of a coordinated multi-phase programme, with each block presenting different access, sequencing and logistical requirements. KGK provided safe and reliable scaffold access across Blocks 1 to 6, carefully adapting each phase around the existing building layouts, residential access points and surrounding site constraints.
Full-height access scaffolding was installed to support works across the development, with each phase planned to maintain practical access and allow works to progress efficiently across multiple elevations.
Delivering scaffolding across all six residential blocks required careful coordination, consistent standards and detailed planning throughout, demonstrating KGK’s ability to manage a large-scale access package across a complex riverside residential development.
PROJECT DETAILS
LOCATION
Point Pleasant, London
PROJECT TYPE
Large-Scale Residential
SERVICES PROVIDED
Residential Scaffolding Multi-Block Access Scaffold Security Systems Site Coordination
02 / SCOPE OF WORKS
The project included:
Scaffolding and access solutions across six residential blocks
Safe access to multiple working areas throughout the development
Temporary scaffold alarm and security systems across all six blocks
Coordination of labour, scaffold materials and access routes
Ongoing scaffold inspections and access management
Site segregation and protection measures within an occupied residential environment
Phased scaffold works to support the wider construction programme
03 / REQUIREMENTS & CHALLENGES
Delivering the works across six separate residential blocks required detailed phasing and close coordination of labour, materials, scaffold access and specialist security systems throughout the programme.
With the development remaining occupied, KGK had to maintain safe and practical access for residents while minimising disruption and carefully managing interfaces with entrances, pedestrian routes and other ongoing works.
Each phase required coordination with site management and other trades to ensure scaffold erection, adaptations and dismantling progressed efficiently without compromising resident safety, site security or programme requirements.
04 / PROJECT OUTCOME
KGK successfully delivered and managed the complete scaffolding and access package across all six residential blocks as part of one coordinated, multi-phase programme.
The completed works provided safe and reliable access throughout the development while maintaining residential access, site security and coordination with the wider construction programme.
The project demonstrates KGK’s capability to manage large-scale, occupied residential schemes, where multiple working areas, changing access requirements and specialist scaffold-security measures must be carefully coordinated from start to finish.

KGK SCAFFOLDING LTD
Established scaffolding contractor providing safe access solutions across London, Essex, the South East and beyond.
Safe access. Reliable delivery.